1. Vijayanagar Layout
In respect of sites in Sy. No 130, status quo has been ordered in the h'ble highcourt and notice have been served. Case likely to come up for argument shortly. Mean while alternative proposals are also being worked to relocate as was suggested and a meeting was also held on 10/12/2006 to resolve the issues of alternative proposals. As decided in the meeting, for those who opted for alternate sites, registration of alternative sites is completed.

2. Venkatala (Yelahanka) Layout
While efforts were on for procuring lands for an approach Road, BDA has now notified for the outer peripheral road adjacent to the Layout. But unfortunately along with this some more lands including our layout has been notified for Truck Terminus instead of the original location identified in the notified CDP. Objections have already been filed to BDA and a writ petition challenging the acquisition is field along with other members of the welfare association there. Case likely to come up for further argument, admision and orders shortly.

3. Ananthpur (Yelahanka) Layout
Roads and underground drainage system etc., are provided. The ex-landlords are now creating problems to exploit the members / society. Society has already obtained an injunction from Civil Court, Society shall ensure all protection including round the clock security. Cases are also filed in the jurisdictional police station. Evidence & Argument is now in progress. Meeting of the site allotes also held on 6th June 2010 to update the members regarding the issue.

4. Srirampura Layout I Stage
All works including Roads, Culverts, Pavements, UGD, Waterlines, overhead tank and Black topping of Roads are now completed. Electricity along with street lights was commissioned during march 2006. The layout is now made over to BBMP.

5. Srirampura Layout II Stage
  • Electricity for the entire layout along with street lights was commissioned on 23/3/2006.
  • Chip carpeting (Black Topping) of Roads are now completed.
  • Roads, CA and parks were made over to B.D.A vide relinquish deed executed in favour of B.D.A on 11/01/06.
  • Copy of approved layout plan from BDA is now received.
  • Allotment of sites to all eligible site depositors were made on 02/05/2006.
  • Clearance from Karnataka Pollution Control Board is received vide their letter dated 23/05/06.
  • Expert committee for environmental clearance of ministry of environment and forest, New Delhi has cleared the project in the committee meeting held on 18/08/2006.
  • Registration of sites is now completed.
  • Landscaping of Parks is now completed.
  • Planting of Avenue Trees along the roads is also completed.
  • Issue of Khatha form BDA is now almost completed.
  • Many houses has now started coming up.
  • Water lines are now laid for the entire layout by BWSSB for supply of Cauvery water. And it is likely to be commisioned shortly.
  • A meeting of SRP 1 & 2 allotes was held on 2nd December 07 and the Residents Welfare Association was formed & also held there last AGB during June 2010.
  • Gymnasium at CA site was inaugurated on 19th June 2011 along with annul general body meeting of residents welfare association
  • To augment the water supply one more bore well was sunk & commissioned by BBMP with courtesy of local MLA.

  • 6. HBR Layout
  • Civil works like formation of roads, drains, culverts and marking of sites are almost complete.
  • Work of laying water and sewage lines are completed.
  • Soling and Metaling of roads are completed.
  • The entire layout area including roads, parks, CA and sital area are completely filled up to an extent of about 2 meters to avoid water logging.
  • Roads, CA and parks were made over to BDA vide relinquish deed executed in favour of BDA on 20/02/06.
  • Clearance from Karnataka Pollution Control Board is received vide their letter dated 23/05/06.
  • Expert committee for environmental clearance of ministry of environment and forest, New Delhi has cleared the project in the committee meeting held on 18/08/2006.
  • Approved copy of layout plan from BDA is received.
  • Planting of Avenue Trees along the roads is also completed.
  • Allotment of sites to all eligible site applicants ( Seniority up to 266 ) were made on 28/05/06.
  • Registration of sites is now completed.
  • BDA has issued Khathas for all the sites registered at HBR.
  • Power supply along with street lights for the layout is commisioned on 10-08-07.
  • Cauvery water is comissioned by BWSSB
  • Construction of 12 houses are completed & residents have occupied.
  • Construction of more houses are in progress & few more are likely to start.

  • 7. Woods Enclave 1st Stage
  • Laying of UGD & water Lines are completed.
  • Laying of underground electrical cable with transformers are completed. Electric supply along with street lights is now commissioned.
  • Black topping of roads is completed.
  • Planting of Avenue Trees along the roads is also completed.
  • All round compound with an entrance arch ( with security room ) is also completed.
  • Clearance from Karnataka Pollution Control Board is received vide their letter dated 23/05/06.
  • Construction of one house is completed & resident have occupied. One more house is under construction and few more are likely to start shortly.
  • Round the clock security is provided.
  • Construction of Sewage Treatment Plant is completed and likely to be commissioned shortly ( Together for Phase I and II ).

  • 8. Woods enclave 2nd Stage
  • Efforts are on for procurement of additional land.
  • All round compound is completed.
  • Plan was got approved. Works are completed and provisional allotment of sites completed.

  • 9. Nisarga Phase I
  • Plan was got approved. Works are completed and provisional allotment of sites completed.

  • 10. Nisarga Phase II
  • Procurement of Lands are in progress.
  • Since most of the lands proposed for procurement, are govt. grant lands, permission of Govt. is mandatory for purchase. Hence, there is a delay in procurement.
  • BIAAPA Master Plan has been released & this project has been cleared.
  • Plan approval received and works are in progress.

  • 11. Greenfield Gardens Phase 1
  • BIAAPA Master Plan has been released & this project has been cleared.
  • Approval of plan is received and layout Works are now fast progressing.

  • 12. Greenfield Gardens Phase 2 & 3
  • Our other projects at Greenfield Garden Phase II & III are now cleared as Residential Zone.
  • Procurement of land is now almost complete.
  • All round compound and leveling works for formation of roads are now in progress.
  • Approval of plan is received and work has now started for phase II & III phase and layout works are fast progressing.

  • 13. Woods Regency Huttanahalli Project
  • To relocate site depositors for Sampegehalli, Yelanka, Nisarga and Woods Enclave(sus), a new project very near to woods enclave was conceived.
  • Procurement of land for this project is now almost complete. All Round Compound Wall work is now in progress.
  • BIAAPA Master Plan has been released & this project has been cleared.
  • Plan approval received and works are in progress.